How Bitcoin Miners Fund Data Centers for AI

Companies that previously focused primarily on Bitcoin mining are increasingly developing infrastructure for artificial intelligence. Long-term agreements with tech corporations allow them to anticipate future revenue and attract funds for building data centers. However, having a large contract does not necessarily mean that the company has already secured the necessary financing or ensured future profits.
What the $19 Billion TeraWulf Contract with Anthropic Means
TeraWulf has entered into long-term agreements with AI developer Anthropic for leasing computing infrastructure at the Justified complex in Kentucky.
The total value of the payments stipulated by the contract amounts to about $19 billion for the initial 20-year lease term. The company plans to provide Anthropic with approximately 401 MW of computing infrastructure, with phased commissioning scheduled from the end of 2027 to the second quarter of 2028.
If we hypothetically divide $19 billion over 20 years, it amounts to about $950 million per year. However, this figure represents a simple average and not a forecast of TeraWulf's annual revenue or profit. Actual cash flow will depend on the commissioning schedule of the facilities and the terms of the lease agreements.
At the same time, construction expenses arise before the facilities start generating regular payments. Therefore, the company needs to finance the construction, equipment procurement, and infrastructure connection before the full launch of the data centers.
The Role of Google's Credit Support
On November 4, TeraWulf announced agreements with Google providing credit support for certain Anthropic lease obligations at the Justified complex.
This support can enhance the project's attractiveness to creditors as it reduces some of the risks associated with the potential non-fulfillment of obligations by the tenant.
However, its effect is limited by the terms of the contracts. In particular, the support comes into effect after the launch of the last data hall as stipulated by the respective lease agreement.
In the event of certain breaches of payment obligations by Anthropic, Google may assume the lease or, subject to established conditions, agree to terminate the contract with the payment of the stipulated compensation.
Thus, Google's involvement does not mean that the company guarantees reimbursement of all TeraWulf's construction costs or the full payment of the lease regardless of circumstances.
Meanwhile, the cost of borrowed capital remains an important factor for financial results. For example, a change in the interest rate by one percentage point on an assumed debt balance of $3.5 billion changes annual interest expenses by $35 million. This is a calculated illustration, not an assessment of TeraWulf's actual costs.
How IREN Pays for AI Infrastructure Equipment
Another financing model is used by IREN, which is developing cloud computing services for artificial intelligence.
In November 2025, the company signed a five-year contract with Microsoft worth about $9.7 billion, providing for a client prepayment of 20% of the agreement amount.
In June 2026, IREN also closed a deal to finance the purchase of graphics processors for $3.65 billion.
Together with the client prepayment, this deal provides $5.59 billion out of the $5.81 billion GPU expenses stipulated by the Microsoft contract. Thus, the described structure covers about 96% of the equipment cost.
IREN reported two financing cost indicators:
6% – the weighted average cost of attracted debt capital
3.31% – the estimated average cost of the entire financial package, including client prepayment
The difference is explained by the fact that the client prepayment is included in the calculation as a source of financing with a zero interest rate. Therefore, the 3.31% figure does not mean that IREN can borrow money from creditors at such a rate.
Client advances reduce the need for other sources of capital but are not pure profit. The company is obligated to provide the paid services under the agreed terms.
What Financial Obligations IREN Retains
According to the quarterly report from November 5, IREN estimates the remaining planned capital expenditures for the 2027 fiscal year at approximately $15 billion.
The company presented the following structure for their proposed financing:
Source of Funds | Amount |
Cash, including restricted funds, committed financing, and client prepayments | $9 billion |
Additional financing the company plans to raise | $6 billion |
Total | $15 billion |
The first category does not consist solely of free cash on accounts. It also includes committed but not yet drawn credit funds and client advances stipulated by contracts, which may be received later.
IREN plans to raise an additional $6 billion through equipment and data center loans, new client prepayments, and other capital sources. The availability of such financing will also depend on market conditions.
The company has also postponed the target annual revenue level, recalculated at current rates – over $4 billion – from the end of 2026 to January 2027, allowing for a possible extension to February. This figure does not represent already received annual revenue.
Why Large Contracts Do Not Guarantee Profit for Shareholders
Long-term agreements with technology companies help data center operators justify investments and attract creditors. However, the final profitability of projects depends not only on the cost of contracts.
Financial results are influenced by construction timelines, equipment costs, the cost of borrowed capital, the loan repayment schedule, and the actual start of client payments.
If the company needs to issue new shares to expand its business, this could also alter the stakes of existing shareholders. Selling accumulated Bitcoin represents another possible source of funds, but its volume will depend on the cryptocurrency's market value and the operator's financial needs.
Therefore, when evaluating Bitcoin miners' transition to AI infrastructure, it is important to compare not only the announced contract values but also the amount of already raised financing, remaining capital expenditures, and project launch timelines.
These indicators allow determining how capable future client payments are of covering construction costs, debt servicing, and further business development.
This material is prepared solely for informational purposes and does not constitute financial advice or a recommendation.